    RESIDENTIAL GENERAL CONTRACTING · Ontario, Canada

    A $48,000 kitchen renovation, paid in five proof-backed stages

    A homeowner and a general contractor agree a full kitchen gut-and-rebuild. Instead of a 30% deposit up front, the job is broken into five milestones with photo and inspection proof attached to each release.

    The job

    • •Full gut of a 1970s galley kitchen: demolition, electrical and plumbing rough-in, drywall, cabinetry, counters, appliances and final finishing.
    • •Contract value of $48,000 including materials, with three named subtrades (electrical, plumbing, counters).
    • •Expected duration of nine weeks, with a hard deadline before a family event.

    Where the payment risk sat

    • •The contractor originally asked for 40% up front to cover cabinet ordering. Ontario has no statutory residential deposit cap, so nothing stopped the request — but it put $19,200 at risk before a single tool came out.
    • •The homeowner had no leverage after the deposit cleared. A bank wire is final the moment it sends.
    • •A third-party escrow service quoted a percentage fee plus a multi-day release window, which would have stalled the cabinet order.

    How it was structured

    • The homeowner set up the agreement, entered five milestones, and set the required proof for each one.
    • A 10% deposit was capped at $4,800 — enough for the cabinet order, not enough to fund the contractor's previous job.
    • The contractor received a link, reviewed the milestones and the proof requirements, and confirmed before work started.
    • Funds sat in a contract the homeowner deployed from their own wallet. PictoSafe never held them.

    The milestone schedule on $48,000

    10%$4,800

    Deposit — cabinet order placed

    Proof required: Signed contract + supplier order confirmation

    Fee on this release: $12.00

    20%$9,600

    Demolition and disposal complete

    Proof required: Before/after photos + dumpster receipt

    Fee on this release: $24.00

    25%$12,000

    Electrical and plumbing rough-in passed

    Proof required: Municipal inspection sign-off + subtrade lien waivers

    Fee on this release: $30.00

    30%$14,400

    Cabinets, counters and appliances installed

    Proof required: Photos of each run + product invoices

    Fee on this release: $36.00

    15%$7,200

    Punch list cleared and site cleaned

    Proof required: Walkthrough video + final lien waivers from all subs

    Fee on this release: $18.00

    What the payments cost

    Contract value
    $48,000
    PictoSafe fee — 0.25% across 5 releases
    $120.00
    Estimated blockchain network fees (paid by you to the network)
    ~$12
    Same job at a typical third-party escrow rate of 1.5%–3%
    $720 – $1,440
    Difference
    $588 – $1,308

    The 1.5%–3% figure is a general range for third-party escrow and trust-account services, used here for arithmetic only. It is not a quote from any named provider, rates differ by provider and by deal size, and you should confirm current pricing directly with whoever you are comparing. Network fees vary with blockchain conditions.

    Why the structure works

    • Five releases at 0.25% each — the fee is charged on the amount released, not on the contract value up front.
    • The rough-in release was the one that mattered: the inspection sign-off was the condition, so the money did not move until the municipality passed the work.
    • Every subtrade lien waiver was attached to a release, so no unpaid sub could lien the property after final payment.